Billd Teams Up with American Express to Help Suppliers Extend Flexible Finance Terms Across U.S. Construction Industry
Blog
/
Feed, Payments, Project Management

Substantial Completion 101: Everything You Need to Know as a Subcontractor

Read time: 5 minutes
Published: April 13, 2022
Last updated: November 04, 2022

 

For many construction projects, owners want to begin using or occupying the building as soon as possible — even if there are still minor details that need to be completed. For that reason, many contracts include the term “substantial completion.” Substantial completion refers to when the building can be used for its intended purpose, even if it is not considered absolutely complete. 

But what makes a project substantially complete, and what does that mean for the subcontractors involved in the project — including when they get paid? Find out below. 

What Is Substantial Completion?

In construction, substantial completion is a legal term often used in contracts between project owners and contractors. It marks the point when the project is considered sufficiently complete. In general, this means that only minor, corrective, or warranty work remains. 

Why is substantial completion important for contractors and subcontractors? Typically, substantial completion marks the point of the project when the owner is responsible for paying the contractor or subcontractors the remainder of their fees. 

How Is Substantial Completion Determined? 

There is no set definition of substantial completion. However, many states have adopted the definition from the American Institute of Architects (AIA), which states that substantial completion is “the stage in the progress of the work when the work or designated portion is sufficiently complete in accordance with the contract documents so that the owner can occupy or use the work for its intended purpose.”

This still leaves room for interpretation, so many project owners aim to specify what marks substantial completion in the project contract. For example, the owner may decide that substantial completion is reached when the certificate of occupancy is signed. Alternatively, the owner and contractor may develop a checklist that includes the items that must be completed to reach the substantial completion milestone. In addition, many contracts will call for a signed certificate of substantial completion to certify when the building is ready for use. 

In any case, it’s important that contractors and subcontractors understand how substantial completion is defined for each project, so they can know when to expect payment — and what to do if they don’t receive that payment on time. 

substantial completion

Who Signs the Certificate of Substantial Completion?

If the project owner opts to issue a certificate of substantial completion or the contractor requests one, it is the responsibility of the architect on the project to inspect the site and issue the certificate. The certificate of substantial completion also includes a list of items remaining to be corrected or completed, as well as the timeline allotted for those items. Once the terms are agreed upon, the architect, contractor and owner sign the certificate. 

The certificate of substantial completion is different from a certificate of occupancy. The certificate of occupancy is issued by a local building inspector. This establishes that the building is safe to occupy and utilize. 

Substantial Completion vs. Final Completion

Substantial completion and final completion are the two final phases of a project. Substantial completion refers to when the building can be used for its intended purpose. Final completion occurs when the project is 100% complete and requires no additional work. 

After the point of substantial completion, there are still some tasks that need to be completed. Often, these are punch list items that could include minor repairs, cleanup, or installations. 

How Substantial Completion Affects Subcontractors

Substantial completion is an important milestone for subcontractors, because at that point they are entitled to payment. In fact, at this point, non-payment could be considered a breach of contract. 

In some cases, contracts will include additional stipulations that might withhold a portion of the payment until the final completion. However, in general, contractors and subcontractors are able to receive payment when the project reaches substantial completion. 

Subcontractors should also be aware that when the project reaches substantial completion, warranty periods commence and some limitation periods begin to run. 

Effects on Warranties, Claims, Liability and Deadlines — What Subs Need to Know

The point of substantial completion triggers deadlines and critical dates in the construction timeline, such as the timelines for claims and warranties. 

Warranties 

The clock for warranty periods (also commonly known as one-year correction periods) begins once substantial completion has been established. During a warranty period, subcontractors are contractually obligated to correct defects in their work or materials. 

Claims and Liability 

Substantial completion also begins the timeline for the statue of repose. This establishes a time period during which an owner can make a claim for defects. In many states, the point of substantial completion also begins the clock for construction lien claims and payment bond claims. 

However, substantial completion also marks the point when contractors and subcontractors are released from certain types of liabilities, like construction delay claims and liquidated damages. At this point, a contractor also cannot generally be held liable for material breach of contract, since the project has performed sufficient work to get the project to this point. 

Worried About Not Getting Paid on Time? Billd Can Help

Defining substantial completion early in the project can be beneficial to general contractors and subcontractors. In that case, everyone knows exactly when to expect payments and when certain timelines are triggered. 

However, because substantial completion is not always concretely defined, there is still a possibility of payment delays. And if contractors aren’t paid on time, they may not be able to pay their subcontractors or suppliers on time. 

If you’re worried about not getting paid on time, Billd can help. With Billd, you can close any potential cash-flow gaps and reduce your stress about when you will get paid. To learn more about how we can work with you to help you keep projects and payments on track, contact us

About Billd: At Billd, we provide a payment solution that enables commercial construction contractors to free up cash for material purchases while enjoying the flexibility of 120-day payment terms. You get financing for commercial materials upfront with the freedom to pay it back at your own pace. Learn more about how we can help eliminate your company’s cash-flow problems so you can win more bids and grow your business.

Learn More

FAQs

What is substantial completion?

Substantial completion is the point when a project is considered sufficiently complete, as agreed to by project owners and contractors. Typically only minor, corrective, or warranty work remains, and the owner is responsible for paying contractors the remainder of their fees.

How is substantial completion determined?

There is no set definition to define substantial completion. Many states have adopted standards from the AIA, but there is still room for interpretation, therefore, many project owners specify what marks substantial completion in the project contract.

Who signs the certificate of substantial completion?

If the project owner opts to issue a certificate of substantial completion or the contractor requests one, it is the responsibility of the architect on the project to inspect the site and issue the certificate. Once the certificate terms are agreed upon, the architect, contractor, and owner sign the certificate.

What is the difference between substantial completion and final completion?

Substantial completion refers to when the building can be used for its intended purpose. Final completion occurs when the project is 100% complete and requires no additional work.

What is the difference between a certificate of substantial completion and a certificate of occupancy?

A certificate of substantial completion includes a list of items remaining to be corrected or completed, as well as the timeline allotted for those items. A certificate of occupancy is issued by a local building inspector, and establishes that the building is safe to occupy and utilize.

Robbie ReynoldsVP of Business Development

Are you ready to unlock more working capital for your business?

Related posts