Build a Working Capital Strategy that Strengthens Your Financial Future:
Blog
/
Feed, Project Management

Change Orders: Different Types, How They Work, and What to Include

Read time: 5 minutes
Published: May 10, 2023
Last updated: October 18, 2023

Changes to contractual agreements can become necessary at any time during the life of a construction project. Between the signing of the original contract and the completion of work, dozens of changes may be requested regarding the project’s schedule, scope of work and budget. Change orders are the official documents used to make changes happen.

What Is a Change Order?

A change order is an essential document that is brought into play during the course of the construction process. It is used to propose and get approval for any change that deviates from the original contract.

What to Include in a Change Order

A change order typically includes the common elements listed below. These will help the project owner or architect approve a proposed change. (The original contract may specific a particular change order form to be used, and may instruct how that form should be submitted. Common forms include the AIA G701 Change Order and ConsensusDocs 795.)

  1. Project and contact information, including:
  • Contract number
  • Project name and address
  • Change order number (each project’s change orders should be numbered in a sequence)
  • Owner’s name and contact information
  • Prime contractor’s name and contact information
  • Name and contact information of contractor submitting the change order
  1. Description of the requested change compared to the original contract

This is where the proposed work change – and the reasons for that change – should be described in as much detail as possible.

3. Updated schedule

The document should include the new schedule that results from the change. The new schedule should state the number of days needed to complete the change, and the date when the change will be finished.

4. Cost of the change

The document needs to include the resulting cost of the proposed work modification. This includes positive and negative charges, overhead, tax, insurance, profits and any other costs associated with the change.

5. Updated contract value

The document should include:

  • The original contract value
  • The value of all past approved change orders (if any)
  • The cost of the current change order
  • The new proposed contract value (including all of the change orders, positive or negative)

Types of Change Orders

Contractors use various types of change orders to collaborate with project owners. Here are the four most common types:

Lump Sum

A lump sum change order is used when the change in the work scope can be quantified with a firm price, resulting in an overall increase in the expense of the project. It can occur when the project owner or a hired contractor finds conditions that warrant a change in work scope.

Zero Cost

This type of change order does not change the contracted price, but is used to document scope- of-work changes that do not affect the contract value.

Time and Material (T&M)

A T&M change order occurs when the entire cost of the proposed change cannot be estimated. In this case, contractors are to track their time spent working on the change, as well as any costs associated with needed materials or equipment.

Unitary Cost

A contractor usually will negotiate this type of change upfront, before any change-related work begins. It is based on additional scope of work that can be defined by specific measurement units. The contractor must track completed work based on those specified units.

How Does the Change Order Process Work?

Prior to execution, the typical change order process looks something like this:

Step 1: The contract is signed. This document outlines the project’s scope, schedule and budget that have been agreed upon.

Step 2: An issue is raised. Often, contractual agreements need to be changed due to reasons such as:

  • Material procurement issues
  • Regulatory changes
  • Owner-initiated changes
  • Design errors, omissions or alterations
  • Less-than-ideal site conditions

Step 3: A change is proposed. Someone proposes a solution to fix or manage the issue that was raised, and relevant parties review the proposal. At this point, subcontractors may also be asked to estimate the change’s impact on the project budget and timeline.

Step 4: The proposed change is reviewed. The owner evaluates the change and may ask for additional information for clarification in the form of an RFI. (Ideally, the original contract will specify how much time the project owner has to accept or reject a proposed change, or request additional documentation.)

Step 5: The change is agreed upon. All appropriate parties agree on the proposed change. Then the party requesting the change prepares the document to amend the original contract. 

Step 6: The original contract is amended. All appropriate parties sign the document to amend the contract. Then the contractor and subcontractors are responsible for notifying all workers of the finalized changes.

Be aware that the change order process does not necessarily go this smoothly every time. Whenever a contractor requests a change (Step 3 above), the project owner, general contractor or architect can decide to approve the change, counter the change, deny the change, or make a decision to hire someone else.

The Best Way to Handle Change Orders

When you’re hit with a change, multiple factors affect how you should approach the situation. You can adopt different strategies based on how the change arose, and who on the project is responsible for paying for it. Learn about some common reasons for change orders, and to read strategic advice on how to approach specific scenarios.

Interested in Learning About Other Important Construction Documents?

Then make sure to check out these additional blog posts from Billd:

About Billd: At Billd, we provide a payment solution that enables commercial construction contractors to free up cash for material purchases while enjoying the flexibility of 120-day payment terms. You get financing for commercial materials upfront with the freedom to pay it back at your own pace. Learn more about how we can help eliminate your company’s cash-flow problems so you can win more bids and grow your business.

Learn More

FAQs

What is a change order in construction?

A change order is a document used to propose and get approval for any change that deviates from the original agreed-upon contract.

What are the types of change orders?

The four most common types of change orders in construction are: lump sum (when the change can be quantified in price); zero cost (no change in price); time and material (cost cannot be estimated); and unitary cost (a change in scope that can be defined by measurement units).

How does the change order process work?

The change order process typically follows these steps: 1) the contract is signed; 2) an issue is raised; 3) a change is proposed; 4) the proposed change is reviewed; 5) the change is agreed upon; 6) the original contract is amended.

What is the best way to handle change orders in construction?

How you approach a change order should change based on the situation. Different strategies work better depending on how the change arose and who on the project is responsible for paying for it.

Jesse WeissburgCCO & Co-Founder of Billd

Jesse Weissburg is an accomplished business development leader with experience across a variety of industries — including finance, real estate development, construction and renewable energy. With Billd, he uses his experience and knowledge to help contractors grow their businesses by fixing the broken payment cycle in the construction industry.

Are you ready to unlock more working capital for your business?